Work on controversial Bansadhara project resumes at Odisha-Andhra border

A fact-finding team, headed by Bhabani Kant Jena, Superintending Engineer, Water Resources, Berhampur, visited the site on Friday where the construction work is being done by the Andhra Pradesh government.

Odisha, Andhra Pradesh, Odisha Andhra Pradesh border, Bansadhara, Bansadhara project, Polavaram, Ketragadda, Indian Express, India news Even as the dust raised over Polavaram is yet to settle down, the Andhra Pradesh government has resumed the controversial Bansadhara Project-II at Ketragadda, a village along Odisha-Andhra border, without intimating Odisha.

Even as the dust raised over Polavaram is yet to settle down, the Andhra Pradesh government has resumed the controversial Bansadhara Project-II at Ketragadda, a village along Odisha-Andhra border, without intimating Odisha. Andhra government started work without intimating Odisha despite the issue being pending with the Bansadhara water dispute tribunal. The work was stalled for the last six years, officials said.

Watch What Else Is Making News

A fact-finding team, headed by Bhabani Kant Jena, Superintending Engineer, Water Resources, Berhampur, visited the site on Friday where the construction work is being done by the Andhra Pradesh government.

The construction work of the project was started by the AP government in several places, including Ketragadda and Hiramandalam, Jena said.

Subscriber Only Stories
JK Cement’s SPSU Udaipur Launches ‘Golden Batch 2022’ In Collaboration Wi...Premium
Appendicitis in Children- A new lifestyle disorderPremium
Re-Defining The Tradition In Folk Art: An Art Educator’s PerspectivePremium
Symbiosis School of Sports Sciences (SSSS) launches undergraduate program...Premium

“We will submit the report with photographs of the construction work to the government soon,” he added.

The government had sent the fact-finding team to the site after the executive engineer, Paralakhemundi intimated it about the construction work before disposal of the case by the water dispute tribunal.

“We submitted reports to the government when they started the work on October 10,” said B K Panda, executive engineer (water resources) Paralakhemundi.

Panda and retired chief engineer Arun Padhi were part of the fact-finding team.

Advertisement

When the Andhra government proposed to divert the river water from Katragadda to Hiramandalam reservoir under Bansadhara Project-II some years ago, Odisha government had strongly opposed the move.

First published on: 08-11-2016 at 03:41:14 pm
Next Story

Mother of missing JNU student meets Rajnath Singh

Latest Comment
Post Comment
Read Comments
Advertisement
Advertisement
Advertisement
X