Centre ‘delays’ Pune Metro work, but Maharashtra, PMC and PCMC prompt in transferring land for project

On Tuesday, the Army said the delay was because the state government had not suggested an alternative land in lieu of the land to be acquired. Metro officials, however, expressed surprise at the Army’s contention.

Written by MANOJ MORE | Pune |
Updated: January 5, 2021 4:28:27 pm
Centre ‘delays’ Pune Metro work, but Maharashtra, PMC and PCMC prompt in transferring land for project Since the project started 20 months ago, the state government and the two municipal corporations have collectively handed over 33 hectares of land. (File photo)

While the central government is yet to transfer land for Pune Metro, delaying part of the project for months, the state government, Pune Municipal Corporation (PMC) and Pimpri-Chinchwad Municipal Corporation (PCMC) have been prompt in ensuring that the required land is made available without much hassle. Officials of MahaMetro, the implementing agency for the project, said the crucial support from the three bodies has helped them push the project, but it has run into a hurdle because of the delay by the Defence Ministry.

Initially, Pune Metro officials were looking for 41 hectares of land for implementing the project. Since the project started 20 months ago, the state government and the two municipal corporations have collectively handed over 33 hectares of land. “The total land required from the state government, the two local civic bodies and private parties stood at 37 hectares. Of which, 33 hectares or 88 per cent of the land has been acquired. And the remaining 12 per cent will be acquired soon,” said a senior official of MahaMetro.

Around 4 hectares of private land are also needed for the Metro project. “The process is underway. We are hopeful about acquiring the land in the near future,” said the official. The Pune Metro project also needs approval from the Defence Ministry for around 4 hectares of land in the Khadki Cantonment area. As reported by The Indian Express, the proposal for acquiring 4 hectares or 10 acres of land has been pending with the Defence Ministry for 10 months. Both Union Minister Prakash Javadekar and Pune MP Anil Shirole are pursuing the issue with the Defence Ministry.

On Tuesday, the Army said the delay was because the state government had not suggested an alternative land in lieu of the land to be acquired. Metro officials, however, expressed surprise at the Army’s contention. “At a meeting with Defence Minister Nirmala Sitharaman, Chief Minister Devendra Fadnavis had promised that if the Army needed land in Ahmednagar, the government will provide it to them without any delay. The CM’s response came after the Army requested an alternative land in Ahmednagar area,” said a Metro official.

MahaMetro officials said they have been able to push the Metro work forward because of support from the state government and local civic bodies. “The state government and local civic bodies have offered us excellent support for the Metro project. Had they not transferred the land in time, we would not have been able to take the project forward,” said MahaMetro Executive Director Ramnath Subramaniam.

“We are looking for similar support from the Defence Ministry. We hope our proposal will be approved by the Ministry as soon as possible,” he said. Metro officials said if the project was delayed further, it would not be able to meet its 2021 deadline.

Start your day the best way
with the Express Morning Briefing

📣 The Indian Express is now on Telegram. Click here to join our channel (@indianexpress) and stay updated with the latest headlines

For all the latest Pune News, download Indian Express App.

  • The Indian Express website has been rated GREEN for its credibility and trustworthiness by Newsguard, a global service that rates news sources for their journalistic standards.
Advertisement
Advertisement
Advertisement
X