Unitech to refund Rs 3.33 crore to homebuyer

The NCDRC asked the firm to refund the payment of Rs 3.33 crore made by the complainants while purchasing the flat and compensate them in the form of interest at 10 per cent per annum with effect from 2012.

By: PTI | New Delhi |
January 29, 2017 1:35:36 pm
unitech, unitech developers, unitech hi tech developers, uni tech refund, NCDRC, unitech consumer disputes, unitech refund home buyer, unitech group, unitech group refund, unitech possession refund, National Consumer Disputes Redressal Commission, unitech consumer court (Source: File Photo)

The apex consumer commission has directed real-estate major Unitech Hi-Tech Developers Ltd to pay over Rs three crore to a couple for failing to give them possession of an apartment booked under one of its housing projects at Noida in 2010. The National Consumer Disputes Redressal Commission (NCDRC) asked the firm to refund the payment of Rs 3.33 crore made by the complainants while purchasing the flat and compensate them in the form of interest at 10 per cent per annum with effect from 2012. The commission, while deciding the complaint, rejected the claim of Unitech group of companies that the delay in handing over the flats to the buyers was on account of agitation by farmers and shortage of labour.

Watch What Else Is In News?

According to the complaint, the couple had booked a residential flat in project Burgundy, developed by Unitech in Sector 96-98 in Noida and were allotted the apartment on Level 6 in Tower-1 on August 27, 2010 for a total consideration of Rs 3.39 crore, out of which the complainants had already paid Rs 3.33 crore to the firm.

“As regards the alleged shortage of labour, no material has been placed on record to show that it (Unitech) could not get adequate work force to complete the construction of the flats despite efforts having been made in this regard,” the NCDRC said.

Subscriber Only Stories
Re-Defining The Tradition In Folk Art: An Art Educator’s PerspectivePremium
Symbiosis School of Sports Sciences (SSSS) launches undergraduate program...Premium
MIT World Peace University launches Five-Year Integrated B.Tech with MBA ...Premium
Bring Home The Ultimate Solution For The Whole Family With Airtel Xstream...Premium

Regarding the claim of delay due to farmers agitation, the commission said, “…there is no evidence of the work at this particular site having been halted by farmers. No affidavit of the contractor engaged by the opposite party for construction of the flats in this project has been filed to prove that he had to halt the work on account of agitation by farmers.”

📣 Join our Telegram channel (The Indian Express) for the latest news and updates

For all the latest Business News, download Indian Express App.

First published on: 29-01-2017 at 01:35:36 pm